Prorentus project of temporary platform for power plant

BRIEF DESCRIPTION

Designing a framework for overlay support. Using combination of formwork and shoring engineering solutions.

Prorentus engineers chose to use: Layher TG-60, Paschal Logo 3, Paschal Deck systems in this project.

PROJECT DESCRIPTION

Project Type Industrial Building
Client “Aukeda”
Completion Date 2019

SCOPE OF WORK

  • Design a framework for overlay support of emergency fire pumping station.
  • Project obstacle: uneven surface, already existing columns, as well as metal beams, that will interfere with framework support.
  • Obstruct overlay support. Uneven surface, metal beams.
  • Overlay was supported by tower type scaffolding that bypasses metal beams, using short 1.50m and 1.00m wooden beams.
  • The  obstacle of uneven base surface was solved using soles.
  • Systems used: Layher TG-60, Paschal Deck, Paschal Logo 3
  • Prorentus Ltd. provided the design, calculation, on site supervision.
  • Scaffolding and formwork was supplied by the same company.