Building a multi-floor structure for dome assembly
Building a temporary structure for moving existing equipment around
Building a platform that is movable and can go around
Making safe access to temporary platform floors
Making assembly drawings for consumer to assemble the temporary structure
The main requirement was to design birdcage for dome outer shell assembly. Birdcages are costly and time-consuming structures so we came up with an idea of making the 17-meter-high structure which would follow dome’s shape without unnecessary material in the middle of the structure
TG-60 towers were used as a base frame to stiffen the whole structure. With this solution, the contractor was able to use crane which was in the centre of the dome
Another smaller movable 17-meter-high structure on casters was built so that client could make finishing works on dome
Systems used: TG-60, Allround
Short assembly time
Individual design
Cost-effective and practical complete solution from one source (design, material, supervision)
Using as little equipment as possible
Customer could preview the project in 3D space
Contractor could use a crane in the dome centre, therefore no additional work was necessary to carry materials to the top of the structure where dome was being installed)